hi i am having some issue in MS project progress update of fixed duration task
in the above schedule task-6 slab formwork is started before the predecessor task has finished. say it started on 05-06-2024 and i am updating the progress on end of 12th day i.e 16-06-2024. so in the update task dialouge box when i enter the following details
% of complete as 50%
actual start as -05-06-2024
remaining duration as 12days
actual duration as 12days
once i press enter the result showing as 100% completed as per below picture , instead of showing 50% completion how it is possible i am doing anything wrong here please help .
in the above schedule task-6 slab formwork is started before the predecessor task has finished. say it started on 05-06-2024 and i am updating the progress on end of 12th day i.e 16-06-2024. so in the update task dialouge box when i enter the following details % of complete as 50%actual start as -05-06-2024 remaining duration as 12daysactual duration as 12days once i press enter the result showing as 100% completed as per below picture , instead of showing 50% completion how it is possible i am doing anything wrong here please help . Read More