Planner Premium calculation is strange
Hi,
I encountered a strange behavior of the <% complete> field in the premium planner when you change the <duration> and/or <effort> fields after you started a task, e.g.
Set <start date>=today, <duration>=20 days, <effort>=40hours, <% complete>=50%Then change <duration> and <effort> to accommodate for unexpected delay/scope extension
Doing this, you will end up with a completely broken <% complete> value as shown in the image below.
It seems that the <duration> field is somehow integrated in the calculation of <% complete>, which I feel is odd.
Happy to get some feedback
Lasse
Hi,I encountered a strange behavior of the <% complete> field in the premium planner when you change the <duration> and/or <effort> fields after you started a task, e.g.Set <start date>=today, <duration>=20 days, <effort>=40hours, <% complete>=50%Then change <duration> and <effort> to accommodate for unexpected delay/scope extensionDoing this, you will end up with a completely broken <% complete> value as shown in the image below.It seems that the <duration> field is somehow integrated in the calculation of <% complete>, which I feel is odd.Happy to get some feedbackLasse Read More