Help with Task Duration: Start Finish vs Actual Time worked.
Fairly New to MS Project. I am having a hard time understanding Start to Finish of a TASK vs Duration.
Example: Task was started on Oct 1st and finished on OCT 15th. The TIME it took the Resource person do actual do the task was about 2 hours of work…… BUT the task was not finished till 15 days after it started.
How do I set up this task to NOT measure the resources time spent as (360 Hrs), but still have it show on the GNATT that the task was started on OCT 1 and completed on OCT 15th.
FYI, I am trying to do this for ALL TASKS on my project.
Please Help.
Fairly New to MS Project. I am having a hard time understanding Start to Finish of a TASK vs Duration.Example: Task was started on Oct 1st and finished on OCT 15th. The TIME it took the Resource person do actual do the task was about 2 hours of work…… BUT the task was not finished till 15 days after it started.How do I set up this task to NOT measure the resources time spent as (360 Hrs), but still have it show on the GNATT that the task was started on OCT 1 and completed on OCT 15th.FYI, I am trying to do this for ALL TASKS on my project.Please Help. Read More