MS Project allocation of resources
Hi,
When using ms project, is there any way I can have a maximum work time for a people resource.
My issue is this:
I am planning a diving job using welders. We have 6 welders but only 1 can dive at a time. The amount of time each welder can weld for depends on the depth he is diving to. So for example if he dives to 5 meters, then he can dive for 3 hours. If he dives to 20m, he can dive for 50 mins.
I have multiple locations at multiple depths that have to be welded, which I have broken onto seperate tasks.Can I allocate the 1 resource, ie a welder diver, and adjust the maximum work time for each task/location?
Thanks in advance.
Hi,When using ms project, is there any way I can have a maximum work time for a people resource.My issue is this:I am planning a diving job using welders. We have 6 welders but only 1 can dive at a time. The amount of time each welder can weld for depends on the depth he is diving to. So for example if he dives to 5 meters, then he can dive for 3 hours. If he dives to 20m, he can dive for 50 mins.I have multiple locations at multiple depths that have to be welded, which I have broken onto seperate tasks.Can I allocate the 1 resource, ie a welder diver, and adjust the maximum work time for each task/location?Thanks in advance. Read More