MS ProjtUpdating Actual Start and Finish dates without changing the Scheduled Start and Finish dates
I am trying to set the Actual Start and Finish Dates without affecting the Scheduled Start and Finish dates. I have set the Status date to the date I want, marked the %complete at 50%. When I update the Actual Start Date the Scheduled Start Date is updated to the same date. I need to be able record tasks that have started early or late.
I am trying to set the Actual Start and Finish Dates without affecting the Scheduled Start and Finish dates. I have set the Status date to the date I want, marked the %complete at 50%. When I update the Actual Start Date the Scheduled Start Date is updated to the same date. I need to be able record tasks that have started early or late. Read More