Multiple Task Update Bug – Fixed Work to Fixed Duration
I am having a recent issue where I am unable to highlight the entire schedule and change everything from fixed duration to fixed work and vice versa.
My process is: highlight all tasks (including summaries) > Task Information (Multiple Task Information) > Advanced Tab > Task Type.
In the recent past, this would change the entire schedule to the selected task type. Now, MS Project closes the Task Information window and no changes are made.
Any confirmation that this is a bug, or any fix would be greatly appreciated.
I am having a recent issue where I am unable to highlight the entire schedule and change everything from fixed duration to fixed work and vice versa.My process is: highlight all tasks (including summaries) > Task Information (Multiple Task Information) > Advanced Tab > Task Type.In the recent past, this would change the entire schedule to the selected task type. Now, MS Project closes the Task Information window and no changes are made.Any confirmation that this is a bug, or any fix would be greatly appreciated. Read More