Project Professional Issue Durations days not totalling correctly
Hi there,
I am new to MSP and am setting up a schedule for a house boat build. Duration days are not adding up properly so could somoeone have a look at the screenshot and tell me what I am doing wrong.
Framing says 62.5 days (when is 28 days)
Roof 183 days (when 22days)
Thank you in advance.
Kind regards
Mark
Hi there,I am new to MSP and am setting up a schedule for a house boat build. Duration days are not adding up properly so could somoeone have a look at the screenshot and tell me what I am doing wrong.Framing says 62.5 days (when is 28 days)Roof 183 days (when 22days)Thank you in advance.Kind regardsMark Read More