Reschdule out of order task
Hello everyone
Recently, I encountered a problem in my rescheduling, I have activities which started earlier than their predecessors, and after rescheduling they reschedule as retained logic, when i uncheck split task in option menu, msp ignores them compeletly and wont reschdule their remaining work in my new date, how can i make msp reschdule task remaining work without retaining their network logic?
Hello everyoneRecently, I encountered a problem in my rescheduling, I have activities which started earlier than their predecessors, and after rescheduling they reschedule as retained logic, when i uncheck split task in option menu, msp ignores them compeletly and wont reschdule their remaining work in my new date, how can i make msp reschdule task remaining work without retaining their network logic? Read More