Resources Calender and availibility
Good morning,
Pls assist .. I have a 2 calenders on this project. 1. Fabrication 2. Installation. (I’ve allocated it accordingly to my tasks.)
For this project (SAPPI) my Resources for :
1.’Fabrication’ will only be available from 01/10/2024 – 03/11/2024
2. ‘Installation will only be available from 04/11/2024 – 09/11/2024.
When I change the resource availability as such and when adding my ‘available from’ & available to’ columns in the Resource sheet, it does not come up as such as well as the max shows 0% and not 100% or 200%. Why , what am i doing wrong? @
Good morning,Pls assist .. I have a 2 calenders on this project. 1. Fabrication 2. Installation. (I’ve allocated it accordingly to my tasks.)For this project (SAPPI) my Resources for :1.’Fabrication’ will only be available from 01/10/2024 – 03/11/20242. ‘Installation will only be available from 04/11/2024 – 09/11/2024.When I change the resource availability as such and when adding my ‘available from’ & available to’ columns in the Resource sheet, it does not come up as such as well as the max shows 0% and not 100% or 200%. Why , what am i doing wrong? @ Read More