Scheduled Duration is incorrect: reasons unknown
I have added the screenshot from my project. ofcourse it is an exception that i am defining the tasks in seconds (for example, 0.01 for a task)
1. i am not able to enter anything below 0.01 Hrs. is it the lower limit what can be entered into project ?
2. the 0.01 task duration is shown as 0.02 hrs scheduled duration. this happens only with this particular robot resource based tasks. can some one clarify, where is the error
thanks in advance,
Subash
I have added the screenshot from my project. ofcourse it is an exception that i am defining the tasks in seconds (for example, 0.01 for a task)1. i am not able to enter anything below 0.01 Hrs. is it the lower limit what can be entered into project ?2. the 0.01 task duration is shown as 0.02 hrs scheduled duration. this happens only with this particular robot resource based tasks. can some one clarify, where is the error thanks in advance, Subash Read More