Simple Gantt duratiuon issue
Hi team
We are upgrading our IT and setting up a Gantt to report to the business. Seems simple, using the free Gantt in BI.
Set up a sheet with some dummy data. Piece of cake, right?!
Everything though, is coming up as 1 day duration. it does not matter if I use the end date or duration.
The line I have indicated is is 46 days in duration however, it only shows as 1 day. I can see the data field is set to “count” so I guess that is right as there is 1 thing to count but how do I get it to display the days required.
Or how to I get the end date to work? Getting the same issue there to but it is lfirst or last date, or count. Again, doesnt work.
Hoping for someone can assist
cheers
Hi team We are upgrading our IT and setting up a Gantt to report to the business. Seems simple, using the free Gantt in BI.Set up a sheet with some dummy data. Piece of cake, right?! Everything though, is coming up as 1 day duration. it does not matter if I use the end date or duration. The line I have indicated is is 46 days in duration however, it only shows as 1 day. I can see the data field is set to “count” so I guess that is right as there is 1 thing to count but how do I get it to display the days required.Or how to I get the end date to work? Getting the same issue there to but it is lfirst or last date, or count. Again, doesnt work. Hoping for someone can assist cheers Read More