Total Project Progress % Report & S-Curve Report (E, P, C, C) – MS Project 2019 (Desktop)
Hi All,
This thread is a two part question. The Schedule does not contain any resources, this is purely task driven (Dates & Duration). The client is essentially looking to establish what we had planned and where we actually are within the project (Progress % wise).
1) Generate a Total Project Progress % Report (Example in 1. Total Project Progress %.pdf)
2) Generate an S-Curve Report using the items displayed in the graph axis (Example in 2. EPCC Report.pdf)
INFO before I begin: EPCC contract type (Engineering, Procurement, Construction & Commissioning) it’s a special type of contract, where the Contractor is responsible for all activities for design, procurement, construction, testing and commissioning and also delivery to the end user / customer.
What information and assistance I am looking for from this wonderful community:
1) Generate a Total Project Progress % Report → I have typed out what all is being shown in the PDF. I would like to understand what each item represents as well as how and where to find these items and/or how to create custom fields to show this information as well as if this report would be built within MS Project 2019 or generated through a Visual Report:
Please refer to: 1. Total Project Progress %.pdf
a) Cumulated Late Planned %
b) Cumulated Actual %
c) Cumulated Difference % (Difference between a & b, this you can ignore, fairly straight forward)
d) This Period Late Planned %
e) This Period Actual %
f) This Period Difference % (Difference between d & e, this you can ignore, fairly straight forward)
2) Generate an S-Curve Report → Once again, I have typed out what all data the report is using to display the S-Curve Report. Once again, I would like to understand what each item represents as well as how and where to find these items and/or how to create custom fields to show this information as well as if this report would be built within MS Project 2019 or generated through a Visual Report:
a) Actual % → I believe the is the % Complete field, correct?
b) Cumulative Baseline Early %
c) Cumulative Baseline Late %
d) Cumulative Forecast Early %
e) Cumulative Forecast Late %
Over and above that, I would assume this S-Curve would be a Visual Report as it shows a graph axis of the %, would I be correct in saying this?
Thanking you all in advance.
Hi All, This thread is a two part question. The Schedule does not contain any resources, this is purely task driven (Dates & Duration). The client is essentially looking to establish what we had planned and where we actually are within the project (Progress % wise). 1) Generate a Total Project Progress % Report (Example in 1. Total Project Progress %.pdf)2) Generate an S-Curve Report using the items displayed in the graph axis (Example in 2. EPCC Report.pdf) INFO before I begin: EPCC contract type (Engineering, Procurement, Construction & Commissioning) it’s a special type of contract, where the Contractor is responsible for all activities for design, procurement, construction, testing and commissioning and also delivery to the end user / customer. What information and assistance I am looking for from this wonderful community: 1) Generate a Total Project Progress % Report → I have typed out what all is being shown in the PDF. I would like to understand what each item represents as well as how and where to find these items and/or how to create custom fields to show this information as well as if this report would be built within MS Project 2019 or generated through a Visual Report: Please refer to: 1. Total Project Progress %.pdf a) Cumulated Late Planned %b) Cumulated Actual %c) Cumulated Difference % (Difference between a & b, this you can ignore, fairly straight forward)d) This Period Late Planned %e) This Period Actual %f) This Period Difference % (Difference between d & e, this you can ignore, fairly straight forward) 2) Generate an S-Curve Report → Once again, I have typed out what all data the report is using to display the S-Curve Report. Once again, I would like to understand what each item represents as well as how and where to find these items and/or how to create custom fields to show this information as well as if this report would be built within MS Project 2019 or generated through a Visual Report: a) Actual % → I believe the is the % Complete field, correct?b) Cumulative Baseline Early %c) Cumulative Baseline Late %d) Cumulative Forecast Early %e) Cumulative Forecast Late % Over and above that, I would assume this S-Curve would be a Visual Report as it shows a graph axis of the %, would I be correct in saying this? Thanking you all in advance. Read More