Project Online – Baseline Start and Finish fields are “blank” in the Project Center dashboard
We added 2 columns to the Summary view in Project Center, to show the Baseline Start and Baseline Finish fields. However, both columns in the Project Center are “blank” (empty) for all the projects, although the Baseline has been created for all the projects and the Baseline Start and Finish data is available and shown in each of the projects schedule.
Any assistance will be much appreciated.
We added 2 columns to the Summary view in Project Center, to show the Baseline Start and Baseline Finish fields. However, both columns in the Project Center are “blank” (empty) for all the projects, although the Baseline has been created for all the projects and the Baseline Start and Finish data is available and shown in each of the projects schedule.Any assistance will be much appreciated. Read More